Page 201

Pakistan Bait ul Mal:
PAO: Managing Director

1.  Goal: Pakistan Bait-ul-Mal (PBM) is providing assistance to destitute, widows, orphans, invalid, infirm, and other needy
    persons irrespective of their gender, caste, creed and religion through its ongoing core projects/schemes with an infrastructure
     at district level.
2.  Policy: Pakistan Bait-ul-Mal (PBM) established by PBM’s Act 1991 (amended) is a public sector social welfare dispensation
     organization, which helps poorest of the poor through its poor friendly projects and schemes. PBM is providing assistance to
     destitute, widows, orphans, invalid, infirm, and other needy persons irrespective of their gender, caste, creed and religion
     through its ongoing core projects/schemes with an infrastructure at district.

3.  Outcomes: For the Impact of target population by PBM is providing assistance to destitute, widows, orphans, invalid, infirm,
    and other needy persons irrespective of their gender, caste, creed and religion through its ongoing core projects/schemes
     with an infrastructure at district level. e reeducation of poverty and to help out needy and brilliant subtends to complete terrier.

4.  Budget by Outputs:
                                                                                                    Rs. In 000’
                                       Actual
                          Office                    Budget         Medium Term Budget      Outputs                      Expenditure                    Responsible
                                     2023-24      2024-25     2025-26     2026-27     2027-28
 Pakistan Bait-ul-Mal       Pakistan Bait ul       4,320,000       14,008,528      14,371,546      15,502,550     17,052,805
 (PBM) is the largest      Mal
  social safety network of
 the Federal
 Government
 established through
 PBM Act 1991
 (amended). The
 mandate of
 PBM,provides financial
 assistance to the
 poorest of the poor i.e.
  rehabilitation,
  institutional care,
 shelter,medical
 treatment to destitute
 poor patients suffering
 from the life threatening
 maladies of cancer,
 heart & kidney issues,
 medical
 treatment/surgeries of
 cochlear implant
  patients,financial
 assistance of needy
 widows, orphans,
  invalid, and infirm
  irrespective of their
 gender, sex, caste,
 creed and religion. PBM
 has one Head Office,
 07 Provincial/Regional
 Offices and District
  offices throughout

Page 202

 Pakistan including AJK.
 These field offices have
 been established to
 provide relief to the
 poorest segment of the
 society at their door
  step. PBM runs different
 projects/Schemes like
 162 Schools for
  Rehabilitation of Child
 Labour,165 Women
 Empowerment
 Centres,42 Sweet
 Homes for orphanage
 Children,18 Shelter
 Homes, 26 Khana Sab
 Ke Leay and 1 Great
 Home (for old shelter
 less people) across the
 country including Gilgit
  Baltistan and AJK.

 Total                                      7,674,411      14,008,528    14,371,546     15,502,550     17,052,805

5.  Key Performance Indicators/Targets

                      Key        Delivered   Planned      Outputs                                            Medium Term Target                     Performance     Target      Target
                         Indicators      2023-24     2024-25    2025-26    2026-27     2027-28
 Provision of financial        Overall Targets of     3,184,639      4,118,641     9,678,691    10,646,691      11,711,216
 assistance related to       Pakistan Bait ul
 health and education      Mal
 through Individual        Number of             4505         5514        6617        7278          8006
 Financial Assistance,       beneficiaries of
 Child Support Program,     Individual
 and Orphanages through   Financial
 Pakistan Sweet Homes     Assistance
 and Thalassemia Centre   Education
  for treatment for poor     Number of            3,100,903      4,031,174     9,576,000    10,533,600      11,586,960
  children.                    beneficiaries of
                             Shelter Homes
                        and Roti Sab ke
                        Leay (RSKL)
                      Number of             26,378        25,508       28,000       30,800         33,800
                               beneficiaries of
                   Women Empower
                           Centers (WECs)
                      Number of              4,505         11,792       17,688       19,457         21,402
                               beneficiaries of
                               Individual
                              Financial
                           Assistance
                           Medical

Page 203

Number of              4,229         4600        4800        5280          5808
  beneficiaries of
 Pakistan Sweet
Homes (PSH)

Number of              1,696         1750        2000        2200          2420
  beneficiaries of
 Orphan & Widow
 Support
Programme for
 mothers/guardians
  of orphans/girls
Number of              25           25          28          31            34
  beneficiaries of
 Pakistan Old
Home
Number of              6,721         5569        8500        9350          10285
  beneficiaries of
  Individual
  Financial
 Assistance
 general & SFP
Number of             19,063        19,440       21,384       23,522         23,522
  beneficiaries of
 Schools for
  Rehabilitation of
  Child Labour
 (SRCLs)
Number of             11,643        19,042       19042       20946         23041
  beneficiaries
   (Institutional
  Rehabilitation
 through
 Registered NGOs

Page 204

Privatization Division:
PAO: Secretary

1. Goal: To complete privatization of entities entrusted to the Commission in an efficient and transparent manner within given
            time frame.
2. Policy: Privatization Policy 1994 (under review).
3. Outcomes: To establish a Comprehensive Regulatory Framework for conducting transparent and efficient privatization
                 process with a view to improve corporate governance to achieve the objective of socio-economic development
                     of the Country
4. Budget by Outputs:

                                                                                                                      In Rs. 000’
                                     Actual                                             Budget          Medium Term Budget
     Outputs           Office      Expenditure
                                   2023-24       2024-25     2025-26     2026-27      2027-28
Policy formulation for      Privatization          309,794          355,719       373,575        391,441         391,441
the privatization of       Commission
State-Owned
Enterprises (SOE'S)
and the process of
monitoring & evaluation
Total                                     309,794         355,719       373,575       391,441        391,441

Page 205

  5. Key Performance Indicators/Targets:

                                          Targets     Planned                                                                         Forecast Targets
                                       Achieved     Targets  Output    Key Performance Indicators
                                          2023-24     2024-25      2025-26    2026-27   2027-28

Implementation   Divestment of Pakistan                       Completed
of Privatisation    International Airlines Corp. Ltd.    SOA filed     Buy side due
Program         (PIACL):                               with SECP    Diligence
                                               on March     completed in
                                                     28,2024.      Oct 2024.
               • Approval of draft SOA by PIA     SECP
                 BoD.                             sanctioned     Finalization &
               • Filling & approval of SOA by      SOA vide     approval of Bid
                SECP.                          Order dated   documents
               • Publication of EOI.             May 03,      completed in
               • Issuance of SOQs                 2024.        Oct 29 2024.
               • Pre-qualification of Interested       EoI
                     Parties (IPs).                      Published     Approval of
               • Bidding/Closure.                on April 02    Reference Price
                                       & 15, 2024.   by Federal
                                       On june 03,   Cabinet
                                                    2024, PC      finalized on Oct
                                                 Board       31 2024.
                                                    decided to
                                                               pre-qulify      Bidding
                                                                six (06)       conducted on
                                                           interested     Oct 31 2024 but
                                                               parties.        not materialized.             -                    -                  -
                                                          Pre-qualifed
                                                     Bidders      Panned
                                                   (PQBs),      Targets
                                                      given
                                                  access to     Extension of
                                                                Virtual Data  FASA with FA
                                       Room
                                               (VDR) on      Publication of
                                                June         EOI.
                                                  07,2024 for
                                             Buy side       Pre-qualification
                                          Due            of interested
                                                           Diligence.      parties (IPs)
                                                      Bidding
                                                       held on 31st   Buy side due
                                                        Oct. 2024.     diligence
                                                      Bid
                                                      submitted     Approval of
                                                 by only one   Reference Price
                                            PQB.        by Federal
                                                                  Cabinet
                                                                     Bidding

Page 206

                                                       Financial
                                                    Closure.

Privatisation of Services                         -
International Hotel Lahore:
• Finalization of consultative                                   -                                  -                    -                  -
  process with Chief Secretary
  Punjab, LDA, PCBL, NICL &
  CCCL to resolve the issue.
Privatisation of House Building      Buy side    To complete the
Finance:                           due     HBFCL
                                          diligence    negotiated sale
   Finalization & approval of Due                                   completed    process within
   diligence.                                           CFY.                                                                                                            -                    -                  -
• Finalization & approval of ITB &
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
Privatisation of First Women      On Feb 06    Targeted for
Bank:                           2024         completion
                                    Federal       during CFY.
• Federal Cabinet approval for                                    Cabinet
  processing the transaction under                                  approved
  IGCT Act, 2022.                                             for
• Finalization & approval of Due                                    processing
   diligence.                                                                                            -                    -                  -                                      the FWBL
• Approval of Transaction Structure                                       transaction
  by Federal Cabinet.                                  under IGCT
• Finalization & approval of ITB &     Act 2022.
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
Roosevelt Hotel, NY-USA                        -        Approval of
Transaction:                                      Transaction
                                                      Structure by
• Finalization & approval of Due                                                  Federal Cabinet
   diligence.
• Approval of Transaction Structure                                                  Marketing Prep
  by Federal Cabinet.
                                                                                                            -                    -                  -• Marketing preparation.                                                          Pre-qualification
• Finalization & approval of JV                         of interested
  agreement.                                            parties.
• Approval of Reference Price by
  Federal Cabinet.                            Buy side Due
• Financial closure.                                  Diligence

Page 207

                                                          Finalization and
                                                   approval of Bid
                                                   docs.

                                                      Bidding.

                                                       Financial
                                                    Closure.
HESCO & GEPCO:                                  -

• Resolution of issues by
  stakeholders.
• Appointment of FA                                                  Completion of
• Finalization & approval of Due                       Bidding                      -                    -                  -
   diligence.                                        process
• Finalization & approval of ITB &                     planned.
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
Negotiation with Etisalat to settle            -         Finalization of                 -                    -                  -
the pending payments on account                  negotiation with
of privatisation of PTCL:                               Etisalat
• Resolution of issues with Etisalat
   to settle the pending payments.
Settlement    of  KES   Power            -        Resolution of                  -                    -                  -
shareholding structure in KE                      issues

Jinnah Convention Centre,                      -         Finalization of     Completion               -                  -
Islamabad:                                           consultation        of Bidding
                                                 process with      process
• Finalization of consultation                                   CDA to resolve    planned.
  process with CDA to resolve their                                                               their
  observations.                                                     observations.
• Finalization & approval of Due
   diligence.
• Finalization & approval of ITB &
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
Pakistan Re-Insurance Co. Ltd.                -                      -          Resolution of   Completion     -
(PakRe):                                                            legacy issues   of Bidding
                                                               by             process
• Appointment of FA                                                                      stakeholders    planned.  -
• Finalization & approval of Due
   diligence.
• Finalization & approval of ITB &
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
 State Life Insurance Corporation            -                      -            After          Completion           -
 (SLIC):                                                                    corporatizatio   of Bidding
                                                           n of SLIC by    process
• Divestment  of up  to 20% GoP                                                       MoC,          planned.
  shares   to  be   initiated   after                                                                    divestment of

Page 208

   corporatization of SLIC by Ministry                              up to 20%
   of Commerce (MoC).                                  GoP shares
• Appointment of FA                                                         to be
• Finalization & approval of Due                                                  initiated.
   diligence.
• Finalization & approval of ITB &
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
Sindh Engineering Limited (SEL):     -                   -                  Resolution of   Completion     -
                                                                     legacy issues   of Bidding
• Resolution  of legacy issues by                                                               by             process
  stakeholders.                                                                      stakeholders    planned.  -
• Appointment of FA
• Finalization & approval of Due
   diligence.
• Finalization & approval of ITB &
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
Pakistan  Engineering Company    -                   -                  Resolution of   Completion     -
(PECO):                                                            legacy issues   of Bidding
                                                               by             process
• Resolution  of legacy issues by                                                                      stakeholders    planned.  -
  stakeholders.
• Appointment of FA
• Finalization & approval of Due
   diligence.
• Finalization & approval of ITB &
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
1223 MW Ballokt Power Plant:

• Resolution     of    issues    by
  stakeholders.
• Appointment of FA                                               Completion
                                                     Resolution of
• Finalization & approval of Due                                             of Bidding                                                             -            issues by                                      -                  -
   diligence.                                                       process                                                     stakeholders
• Finalization & approval of ITB &                                     planned.
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
1230 MW Haveli Bahadur Power
Plant:
• Resolution     of    issues    by                                 Completion
                                                     Resolution of  stakeholders.                                                              of Bidding
                                                             -            issues by                                      -                  -• Appointment of FA                                               process                                                     stakeholders
• Finalization & approval of Due                                       planned.
   diligence.
• Finalization & approval of ITB &
  SPA.

Page 209

• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
Guddu Power Plant (747 MW):                     Resolution of
                                                    issues by
• Resolution     of    issues    by                                                   stakeholders     • Finalization
  stakeholders.                                                   & approval                 Completi• Appointment of FA                                                                                  of Due       Completion     on of• Finalization & approval of Due                                                             -                                diligence.      of Bidding     Bidding
   diligence.                                                                        process                                                           • Finalization                 process
• Finalization & approval of ITB &                            & approval     planned.     planned.
  SPA.                                                                          of ITB &
• Approval of Reference Price by                                  SPA.
  Federal Cabinet.
• Financial closure.
Nandipur Power Plant (425 MW):                   Resolution of      Resolution of   Approval of           -.
                                                    issues by          issues by       transaction
• Resolution     of    issues    by                                                   stakeholders       stakeholders.   structure by
  stakeholders.                                                                                            federal cab.
• Appointment of FA                                              Appointment
• Finalization & approval of Due                                             of FA.                                                             -
   diligence.
• Finalization & approval of ITB &
  SPA.
• Approval of Reference Price by
  Federal Cabinet.
• Financial closure.
    8 DISCOs:                                    Resolution of       Finalization &            -.                 -
                                                    issues by         approval of
• Resolution     of    issues    by                                                     stakeholders.    Due
  stakeholders.                                                                              diligence.
• Appointment of FA
• Finalization & approval of Due                                                Appointment of     Finalization &
   diligence.                                               FA.               approval of
• Finalization & approval of ITB &                                  ITB & SPA.
  SPA.
• Approval of Reference Price by                                Buy side due
                                                                              diligence.  Federal Cabinet.                                                             -
• Financial closure.                                                   Pre-
                                                                                 qualification
                                                                               of interested
                                                                                 parties.

                                                                    Marketing
                                                                     Prep.

                                                                         Bidding.

                                                                          Financial
                                                                       Closure.

Page 210

  Privatisation of Zarai Tariqiati                  Appointment of    Pre-
  Bank Ltd.                                    FA.                  qualification
• Appointment of FA                                                         of  interested                                                           Sell side due
• Finalization & approval of sell                                            parties IPs.                                                          diligence.
  side due diligence.
• Marketing Prep                                 Approval of      Buy side due
• Publication of EOI                                  transaction         diligence.
• Finalization and approval of Bid               -         structure by
  docs.                                           Federal           Approval of
                                                    Cabinet.          Reference• Bidding
                                                                         Price by Fed• Financial Closure.                               Marketing Prep.                                                               Cab.
                                                       Publication of
                                           EOI                Financial
                                                                       Closure.

Page 211

Railways Division:
PAO: Secretary

1.      Goal: To contribute towards provision of safe, reliable, affordable, environment friendly and competitive passenger
              and freight services.
2.      Policy: Our policy is to invest, build and improve railway system mainly focusing on business
                 development and operations, rolling stock availability, infrastructure development and improved governance.
3.     Outcomes: Improved safety, reliability and affordability of railway system in services.
4.     Budget by Outputs:

                                                                                             Rs. In 000’
                        Office         Actual                                             Budget          Medium Term Budget
    Outputs      Responsible   Expenditure
                                   2023-24       2024-25     2025-26     2026-27     2027-28
 Railways Policies     Railways Division       394,200          439,402        457,832                -                       -
 Formulation and
 Implementation
 Railways Services     Pakistan             57,000,000       64,000,000      70,000,000              -                       -
                      Railways
                  (CEO / Sr. GM)
 Pak railways           Additional             1,448,522         5,302,000       7,660,000               -                       -
  infrastructure &       General Manager
 equipment              (Infrastructure)
 development
 services - Other
  Infrastructure
 Pak railways           Additional             827,532         1,639,000        80,000                 -                       -
  infrastructure &       General Manager
 equipment
 development
 services - Signaling
 Pak railways           Additional             7,316,305        23,826,000      10,175,000              -                       -
  infrastructure &       General Manager
 equipment              Infrastructure
 development
 services - Track
 Governance           Director General        130,136          350,000        120,000                -                       -
                MoR
 Pak railways           Additional              42,000           50,000                  -                     -                       -
  infrastructure &       General Manager
 equipment
 development
 services - Regional
 Development
 Business               Additional             1,877,781         1,285,000       3,160,000               -                       -
 Development         General Manager
 Pak railways           Additional            20,436,668       12,548,000      1,220,000               -                       -
  infrastructure &       General Manager
 equipment
 development
 services - Rolling
 Stock
 Total                                   89,473,144      109,439,402    92,872,832

Page 212

5. Key Performance Indicators/Targets

                         Key        Delivered    Planned        Outputs                                            Medium Term Target                        Performance     Target      Target
                             Indicators      2023-24     2024-25   2025-26   2026-27    2027-28
 Railway Policy Formulation        Policies                2            2          3          2            2
                                 Formulation and
                                 Implementation
                               (Numbers)
 Railways Services                Freight Traffic to         7.81           8.83        9.03        9.32           9.32
                             be handled
                                           (Billion Tonn
                                   Kilometers)
                              Passenger              29.8          35.44       36.22        37.4           37.4
                                        Traffic to be
                                handled (Billion
                              Passenger
                                   Kilometers)
                                    Freight Revenue       28.008         27.85       28.47        29.4           29.4
                                   (Rs. in Billion)
                              Passenger            48.278         54.60       55.81       57.63         57.63
                            Revenue (Rs. in
                                           Billion)
                                Other Revenue        12.507          7.55        7.72        7.97           7.97
                                 Receipts (Rs. in
                                           Billion)
                                    Total Revenue         88.793          90         92         95           95
                                   (Rs. in Billion)
                              Improvement in       82%           81         82         83           83
                                     punctuality of
                              Passenger
                                  Services (%)

  Infrastructure development -       Rehabilitation of         70.5           31        244        296          124
 Track                             tracks (KMs)
  Infrastructure development -       Rehabilitation of         0            0          1          0            0
 Stations                           Existing Stations
                               (Numbers)
  Infrastructure development-       Rehabilitation of         22           34         35         35           35
 Bridges                         Bridges (Nos)
  Infrastructure development-       Provision of             1            0          1          0            0
 Shelters                          platform
                                   Shelters (Nos)
  Infrastructure development -    Up gradation of         46           27         30         0            0
 Signaling                          signaling system
                              (KM)

                         Up gradation of          9            4          3          3            0
                                   Signaling
                             System (No.of
                                     Stations)

Page 213

Infrastructure development -      Meterization of          16            0          0          0            0
Electrical power               26000 meters
                              (%)
 Rolling stock availability           Rehabilitation of         1            0          1          1            0
                                  accidental
                                locomotives
                                  Special repair          46            6          5         10           0
                                     of locomotives
                              Procurement of         0            10         87         87           0
                       New Coaches
                             (Numbers)
                              Procurement of         60           250        130         0            0
                       New Wagons
                             (Numbers)
                               Repair and            1184           0         153       1300         1300
                              Maintenance of
                           Power Van, AC
                            and Economy
                                  class coaches
                                (Nos)
                               Repair and            3139          328         0          0            0
                              maintenance of
                           wagons
 Business Development and       Establishment          0            0          0          0            0
Operations                         of Dry Ports /
                                Terminals
                             (Numbers)
 Governance                      Introduction of          50           25         25         0            0
                       ERP (%)
                                   Training and           60           70         50         60           65
                             Developments
                             (Numbers)
                                  Monitoring and         60           60         60         60           60
                                 Evaluation
                               Reports

Page 214

Religious Affairs and Inter-faith Harmony:
PAO: Secretary

1. Goal: Maximum facilitation to Hujjaj / Zaireen, propagation of standardised teachings of
           Islam, harmonization and reconciliation among faiths and sects
2. Policy: Hajj Policy (https://mora.gov.pk/ & https://hajjinfo.org/)
             Iran/Iraq Zaireen Policy
3. Outcome: Propagation of Islam and promotion of interfaith harmony
4. Budget by Output

                                                                                                                      In Rs.000’
                                   Actual
                      Office                    Budget         Medium Term Budget     Output                    Expenditure                Responsible
                                 2023-24      2024-25     2025-26    2026-27     2027-28
  Facilitation and       Hajj Wing            942,761         1,081,730       1,680,921     1,146,879      1,261,567
 arrangement
 services for Hujjaj
 Policy making and   Main Secretariat       436,536         459,045        690,786       704,000       774,400
 administration
 Celebration of         Interfaith             182,246         185,000        178,000       217,800       239,580
  religious festivals    Harmony Wing
  of minorities
 Financial               Interfaith              65,334          100,000         85,000        93,500        102,850
 assistance in       Harmony Wing
 shape of cash
  transfers, small
 development
 schemes,
 scholarships for
  minorities
  Facilitation and     Dawah and                      -             30,350         12,080        33,308         33,308
 management of       Ziarat wing
 Muslim pilgrimages
 beyond Pakistan
 except Hajj, and
 coordination with
 Muslim countries
 and organizations
 on Islamic matters
 Moon Sighting       Research and          5,967            6,500          6,500         7,150          7,865
 Services            Reference Wing
 Addl Allocation for                                         123,821
 ARA 24

 Total                                  1,632,844       1,956,096      2,653,287     2,169,329     2,386,262

Page 215

5.Key performance Indicators/ Targets:

                                         Target    Planned
                Key Performance                         Medium Term Budget     Outputs                        Achieved    Target
                        Indicators
                                       2023-24    2024-25    2025-26    2026-27   2027-28
                         Training for Hujjaj on       100%       100%       100%      100%      100%
                        Manasik-e-Hajj &
                          Administrative aspects
                           of Hajj (as %age of total
                           Hajj quota)

                   Number of airports to be        2            3           3           4           5
                         included under road to
  i). Facilitation and     makkah
 arrangment services
  of Hujjaj              No. of Hujjaj                179,210       179,210      179,210      179,210      179,210
                     Books of               Pak Hajj App    Pak Hajj     Pak Hajj     Pak Hajj     Pak Hajj
                      Manasik e Hajj                         App        App        App        App

                  %age compliance with      100%       100%       100%      100%      100%
                 SPA

                  %age of Complaints        100%       100%       100%      100%      100%
                     and inquiry resolution

                   Number of beneficiaries       4,000         2,202         2,500        2,700        2,900
                                  - cash transfers

   ii. Financial
 assistance in shape   Number of beneficiaries       3,800         1,924         3,000        3,200        3,500
  of cash transfers ,        - scholarships
 small development
 schemes,
 scholarships for      Number of beneficiaries        0           53          30          35          38
  minorities                   - small development
                    schemes

   iii). Celebration of     Number of participants        5,200         5,400         5,400        5,500        5,500
  religious festivals of     in Relligious Festivals
  minorities

Page 216

                     Conference to be             04           4           5           6           7
                       held on (Date of holding    Conference
                      conference)             & 04
                  Number of conferences     Seminars
                   on sectarian harmony

                     No. of Ruet e Hilal            12           12          12          12          12
                    Committee Meetings

iv). Moon sighting
services           %age of Harmony in Eid     100%       100%       100%      100%      100%
                   and Ramzan
                   announcement

                  Number of competitions        9            9           9           9           9
                     arranged seerat
                            literature

                      Seerat conference to be    12th Rabi ul    12th Rabi ul   12th Rabi ul   12th Rabi ul    12th Rabi
                       held on                    Awal         Awal         Awal        Awal          ul Awal
                      (Date of holding
                      conference)

                     Conference to be             4            4           4           4           4
v).Policy making and   held on (Date of holding
Administration         conference)
                  Number of conferences
                   on sectarian harmony

                        Publications of              250          500         600         700         800
                      Maqalat-e-Seerat
                   (Number of copies
                         printed and distributed)

Page 217

Science and Technology Division:
PAO: Secretary

1. Goal: Provision of proper infrastructure, technical and financial support for development of Science and Technology sector
            in Pakistan along with standardization of science and technology related processes and products.
2. Policy: National Science Technology and Innovation Policy 2022
3. Outcome:
4. Budget by Output:
                                                                                                                      In Rs.000’

                                    Actual
                       Office                    Budget         Medium Term Budget    Outputs                      Expenditure                 Responsible
                                   2023-24      2024-25     2025-26     2026-27     2027-28
 Promotion of       D.G, Pakistan            650,002        659,503       701,913        594,499        594,499
 Standards and      National
  Quality              Accreditation
 Assurance.         Council (PNAC),
                   D.G, National
                      Physical Standard
                     Laboratory (NPSL)
               & D.G, Pakistan
                      Halal Authority
                  (PHA)
 Promotion of       Chairman, Pakistan       312,031        414,919       190,293        181,502        181,502
  Alternate Energy    Council of Research
 and Water            in Water Resources
  Quality.         (PCRWR) & D.G,
                     Pakistan Council of
                  Renewable Energy
               & Technologies
                  (PCRET).

 Promotion of        Rector, National          5,862,091       5,941,837      6,158,203       5,617,737       5,617,737
 Higher Education    University of
  in the field of       Science &
 Science and       Technology (NUST)
 Technology       and Rector,
              COMSATS
                       University
                    Islamabad (CUI).
 Formulation/Impl    Ministry of Science       1,294,998       3,140,076      2,698,842       3,242,665       3,242,665
 ementation of     & Technology (Main
  Policy Frame        Secretariat) &
 Work and          Chairman, Pakistan
  Provision of         Council for Science
 Admin Supports.   & Technology
                  (PCST)

 Research and      Chairman, Pakistan       8,951,852       9,317,017      9,097,335       5,373,881       5,373,881
 Development for    Council of Scientific
 Socio Economic   & Industrial
 Development      Research (PCSIR),
                   D.G, National

Page 218

                                Institute of
                            Electronics (NIE),
                        Chairman, Council
                                for Works &
                        Housing Research
                    (CWHR) & D.G,
                           National Institute of
                       Oceanography
                         (NIO)

       Popularization of    Chairman, Pakistan       641,692        861,234       481,532        404,341        404,341
       Science.           Science Foundation
                          (PSF).

       Liaison with        Main Secretariat          527,320        416,000       477,398        456,131        456,131
       International       and Joint Scientific
       Organizations for    Advisor IL
       the Development
       of Science and
      Technology

      Total                                   18,239,986     20,750,586    19,805,516     15,870,756     15,870,756

     5. Key Performance Indicators/Targets:

                                                 Targets   Targets                                                             Medium Term Target
   Outputs      Key Performance Indicators    Achieved  Planned

                                                2023-24   2024-25   2025-26    2026-27    2027-28
                    No. of Testing and Calibration
Promotion of          Laboratories Accredited by PNAC
Standards and                                             250         248         253         258           263
Quality Assurance
                    No. of Inspection Bodies
                      Accredited by PNAC
                                                          16          16          17          18          19

                    No. of Medical Lab. Accreditation
                    by PNAC
                                                          37          38          39          40          41

                    No. of Halal Certification Bodies
                    by PNAC
                                                          11          12          13          14          15

Page 219

                         Certification Bodies (PNAC)                 10          11          12          13          14
                       Proficiency Testing (PNAC)                  4           3           3           3           3
                     Product Certification (PNAC)                 1           1           1           1           1
                         Certification of Persons (PNAC)              3           3           4           4           4
                      Trainings/Courses/Seminars/
                    Webinars (PNAC)                         12          12          12          12          12
                    No. of Testing & Calibration
                      Services Provided by NPSL/NMIP           2,150       2400        2900        3400       3800
                      Physical Working Standards
                       Fabricated/ Calibrated and
                    Reference Materials Developed              5          10          15          20          25
                   (NPSL/NMIP)
                    No. of Training/Workshop
                    Organized by NPSL/NMIP
                                                          10          10          12          16          20

                      On-site Calibrations by NPSL/ NMIP
                                                          42          60          70          80          100
                    No. of Public/Private Sectors
                        Clients Served (NPSL/NMIP)                393         400         580         580         580
                        International Traceability of
                   Equipment (NPSL/NMIP)                   19          10          12          12          12
                        Traceability of in-house
                                                          60          80         100         100           100                   Equipment (NPSL/NMIP)

                                                          9          10          12          14          16                PT Program Organized by
                 NPSL/NMIP
                        Participation in International ILC /
                                                          2           2           3           3           3                PT Programs (NPSL/NMIP)

                    No. Need based Projects
                                                          0           1           4           5           6                   (NPSL/NMIP)

                     Consultancies Provided by
                                                          4           5           7           8           10                 NPSL/NMIP

                   Paper Published (International),
                                                          3           4           4           6           6                 NPSL/NMIP

                   Paper Published (National),
                                                          3           2           4           6           8                 NPSL/NMIP

                      Technical Reports (NPSL/NMIP)              2           2          10          12          12
                     Students Supervised
                                                          10          10          12          12          12                   (NPSL/NMIP)

                MoUs Signed by NPSL/NMIP                3           4           4           6           6
                      Testing of Building Materials by
                                                                                                  -          70         100         100         100
             CWHR
Promotion of          Provide Consultancy/ technical services to      6           6           7           8           2
Alternate Energy and  Public/Private sector organizations in the
Water Quality            field of renewable energy technologies
                  (PCRET)

Page 220

                     Impact factor Journals publications in the
                            field of Advance PV Technologies             2           3           3           4           3
                  (PCRET)
                       Collaboration/signing of MoUs with
                        National/ International                      4           3           5           4           2
                         Universities/ Organizations/ Companies
                  (PCRET)
                PV Panel testing services to                 10          11          15          15           0
                        Public/Private Sector (PCRET)
              MS research projects carried out              4           4           5           6           0
                         at PCRET lab (PCRET)
               PHD research projects carried out            0           2           2           3           2
                         at PCRET lab (PCRET)
                    Arrangement of renewable energy            1           3           5           5           3
                     seminars/ conferences (PCRET)
                       Training programs to
                         installers/users of renewable energy           0           4           5           6           2
                       applications (PCRET)
                 Number of projects with
                         international financial/ technical               3           3           4           4           4
                      cooperation/ organizations related to
                    renewable energy (PCRET)
                     Patents filed in the field of renewable
                    energy technologies                        0           1           2           2           1
                  (PCRET)
                      Prototype development of renewable
                    energy products
                  (PCRET)                                0           3           3           5           5
                    Papers to be published by NUST
                                                              1,700       1900        2050        2200        2350Promotion of Higher
                         Industrial linkage established byEducation
               NUST                                  600         700         800         900         1000in the field of Science
                No of Patent/Copyand Technology
                       rights/trademarks filed by NUST              1,162        1,488        1,810         2,210        2,210
                No of Research Articles to be
                     presented in conferences by NUST           230         300         350         430         550
                    No. of S&T  Policy  studies   /
                      Technical Reports (PCST)                   4           5           5           5           5
                    No. of Technology Foresight
Formulation /         Reports (PCST)                           2           1           1           1           1
Implementation of     STI Policy Briefs by PCST
                                                          12          5           5           5           5Policy Frame Work
                      Evaluation of Individual Research ofand
                        Scientists (No. of ScientistsProvision of
                      evaluated) by PCST                        0                  -          2500        2500        2500Admin Supports
                   Research Productivity Award (incentive
                      given to number of
                       Pakistani Scientists) by PCST                0          250         250         250         250
                      Evaluation of Scientists for Medals &
                    Awards, etc (No. of
                        Scientists evaluated) by PCST               0          50          50          50          50
Research and           Civil Engineering Conference, Exhibitions,
Development for      symposia etc.
Socio Economic     (CWHR)                                 2           3           3           3           3
Development         Other Activities Related to joint
                       Collaboration (CWHR)                      3           3           3           3           3

Page 221

                            Skill Development and Training to
                      Organizations (CWHR)                     3           3           3           3           3
                   Paper Publication (CWHR)
                                                          2           2           2           4           4
                  To coordinate and maintain liaison
                       with international organization and
                           institute for arranging training or
                      experts services (NIO)                      6           4           5           5           5
                  To undertake mission oriented multi-
                         disciplinary research in
                      Pakistan maritime zones (NIO)               5           6           6           5           5
                    Procurement of specialized instruments
                   and equipment,
                        transfer of marine technology, and
                    development of cooperative research
                   program (NIO)                            0           1           1           1           1
                    No. of Clients Served by PCSIR
                                                             21,674       17,700       18,000        19,000       20,000
                 Number of Process developed
                   (PCSIR)                                237         260         275         280         285
                 Number of Process leased-out
                   (PCSIR)                                107         95         100         110         115
                 Number of testing/ calibration
                      services provided by PCSIR                64,113       50,000       51,000        52,000       54,000
                 Number of Patents filed (PCSIR)
                                                          28          28          30          35          37
                 Number of Patents obtained
                   (PCSIR)                                 3           5           5           5           5
                 Number of Students supervised
                   (PCSIR)                                   1,406        780         800         820         850
                 Number of consultancies provided
                         to the industry (PCSIR)                    992         675         680         690         700
                 Number of Feasibility / technical
                       reports prepared (PCSIR)                  319         300         320         340         350
                 Number of Papers published
                         (International) (PCSIR)                    150         135         140         150         155
                 Number of Papers published
                        (National) (PCSIR)                        37          45          50          55          60
                 Number of analytical Equipment
                   Developed (PCSIR)                       138         200         210         220         225
                         Exhibition/ conference/ Seminars
                     organized by PCSIR                       50          85          90          95          100
                   Workshop/ trainings organized by
                 PCSIR                                 146         170         175         180         182
                MoUs signed with industries/
                   academia (PCSIR)                        19          35          40          40          40
                        Interaction with Industries
                   (PCSIR)                                   2,354        2,200        2,400         2,500        2,600
Popularization of      No. of research and development
Science               organizations to be provided with
                      support (PSF)                            90          77          81          85          86
                       Financial Support to Societies/
                       Journals/ Schools by PSF                   1          46          50          51          55
                    No. of Research Initiatives to by
                     undertaken by PSF                        68          46          50          51          55
                       Financial Support to Conferences/
                    Workshops/                              53          55          57          58          59

Page 222

Symposium by PSF

Financial Support to Organize Project
Formulation Workshops
by PSF                                  1           3           5           4           4
Financial Support to Scientific
Societies of Pakistan by PSF                14          10          20          25          25
Literature Search & Supply of S&T
Documents to universities,
R&D Organizations etc by PASTIC          45,528       62,000       63,000        64,000       65,000
No. of Users served by PASTIC
for Document Supply Service.                3,823        4,000        4,200         4,400        4,500
No. of clients served by PASTIC
Library physically                           2,986       10,000       11,000        12,000       13,000
No. of online users served by Library
(PASTIC)                               686,600      92,000       94,000        96,000       100,000
Users served under TISC patent
(query based) (PASTIC)                   119         200         220         240         260
No. of Events (Seminars, Symposia,
Exhibitions) organized
by PASTIC                              37          30          30          30          30
No. of Issues brought out
electronically (PASTIC)                     6           6           6           6           6
No. of Library & Information Professionals/
Researchers trained in the area of
ICT/Research Tools by PASTIC              3,100        3,600        3,800         4,000        4,200
No. of Printing jobs completed
by PASTIC.                              16          30          30          30          30
No. of organizations served regarding
printing services by
PASTIC                                 9          10          10          10          10
No. of records entered in Pakistan
Science Abstracts, PSA
(PASTIC)                                25,500       20,000       22,000        22,500       24,000
No. of Abstract Books/Book
published etc. by PASTIC                   8           5           5           5           5
No. of records created in
Technology databases (PASTIC)            28,678       29,000       30,000        31,000       32,000
No. of specimens identified, curated,
documented/catalogued digitally
documented for database and
preservation in PMNH
Laboratory                               76,356       76,000       77,000        78,000       84,000
No. of collaborations/ MoUS signed
between national and international
organizations by
PMNH                                  6          11          11          12          12
No. of visit in the different areas of the
country for collection of natural history
specimens by
PMNH                                  6          15          18          18          18
No. of research articles/ books/
monographs published in national and
international journals by
PMNH                                  42          72          82          96          116
Workshops / Symposia / Training on
                                       30

Page 223

Taxidermy / Medicinal Plants / Gemstone /                 26          26          32          32
Ore-minerals
Identifications by PMNH
Development/maintenance of
dioramas/displays for public
education by PMNH                       47          53          55          61          61
No of schools/colleges/ universities
students and general
public visiting PMNH                      230,000      200,005      230,005      260,005      300,005
Impart of education through
lectures, public display (PMNH)              62          21          21          23          28

Page 224

  States & Frontier Region Division
  PAO: Secretary

   1. Goal: To administer affairs of the acceding and merged states and matters relating to Afghan Refugees in Pakistan.
   2. Policy: To ensure implementation of Government's policies, regulations and their enactment to the mandated to the
                 Ministry.
   3. Outcome: Managing temporary stay of Afghan Refugees living in Pakistan and maintenance allowance to Ex-Rulers of
                  acceding and merged states.

   4. Budget by Outputs

                                                                                                       Rs. In 000’
                                       Actual
                           Office                   Budget         Medium Term Budget       Outputs                     Expenditure                     Responsible
                                      2023-24      2024-25    2025-26   2026-27      2027-28
    Administrative and      Main Secretariat       210, 659        325,901      342,105     358,866         358,866
     policy formulation
    services
    Allowance for ex-      Ex Rulers              20,460          20,451        21,474       22,547          22,547
     rulers of merged /
    acceded states
    Maintenance of         Chief                 637,241        2,065,919      663,297     695,876         695,876
    Afghan refugees'       Commissionerate
   camps                     for Afghan
                         Refugees
    Formulation /                                 15,307
    Implementation of
    Policy Framework and
    Provision of Admin
    Support
    Total                                    883,667       2,412,271    1,026,875   1,077,289      1,077,289

   5. Key Performance Indicator/ Targets

                                             Targets   Planned
                                                           Medium Term Target
  Outputs    Key Performance Indicators*   Achieved   Targets
                                            2022-23    2023-24   2024-25   2025-26    2026-27
Administration of   Awareness Activities (Observance of
the Ministry and    Kashmir Days)
supporting           e)    5th February-Kashmir Solidarity
political stability        Day                             03          03          04          05          06
of Kashmir and         f)   Youm-e-Shuhada-e-Kashmir
GB                          (13th July)
                      g)   Youm-e-Istahsal (5th August)
                      h)  Observance of Black Day (27th
                        October)
                 Departments administered under GB
                   Council  for  providing assistance  in
                     functioning of GB Government

Page 225

                  7.   Office  of  Accountant  General
                            Gilgit-Baltistan (AGGB)
                  8.   Director  General  Audit  Gilgit-
                           Baltistan
                  9.  Department of Inland Revenue
                            Gilgit-Baltistan
                10. Gilgit-Baltistan          Power
                     Development Board
                  Other Initiatives with updates.
         ➢   Assistance and coordination  in
                       admissions  to  the students  of
                  AJ&K in different Universities of
                        Pakistan  on  AJ&K  reserved
                         seats.
         ➢   Certification of Annex-C required
                     by FPSC for the AJ&K Refugees
                       candidates appearing in the CSS
                    and other examination.
Refugees         Maintenance and support of refugees      7405        7734        8000        8500        9000
Management      coming from IIOK (number of families
                    targeted for support)
Social   services       i.   Filling  gaps    i.e   supply   of      270         270         270         300         320
(e.g.      health,      medicines  in  the  health  care
services)                Delivery System  especially  for
                       marginalized border line/hard to
                      reach areas of AJ&K.
                                      ii.  Command   and   Control    of
                     Department/Sub     units   and
                         provision of health care facilities
                          to civilian population of AJ&K.
                                      iii.  Training  of AJ&K  Civil Medical
                       personnel   in   Pakistan  Army
                        Hospital  with  concurrence and
                       approval  of DMS-1.(Number  of
                       personal Trained).
                           iv.  Supervision   of   execution   of
                   schemes viz Malaria/TB/Leprosy
                          control as well as implementation
                     EPI in AJ&K.

Page 226

Water Resources Division:
PAO: Secretary

1.    Goal: By 2050, make Pakistan water secure while preserving the ecosystem

2.    Policy: To carve knowledge products befitting the needs of water resource management

3.   Outcome: As a sole research organization on water, provide solutions to key water resource issues through action and
                    adaptive research I n collaboration with sectoral stakeholders

4.   Budget by Outputs:

                                                                                                                      In Rs. 000’
                                    Actual                                            Budget          Medium Term Budget                       Office                                Expenditure     Output
                 Responsible
                                   2023-24      2024-25     2025-26      2026-27     2027-28
 Admin support /      Main Secretariat        1,172,414        258,585        640,537        309,313        340,245
 Policy development
 and approval /
  technical support
 Climate resilient    WAPDA and          63,882,740
 Water infrastructure   Provincial
 development           Irrigation
                                                                           59,630,120                     departments for
                          federally funded                         2,171,593                      2,777,965       3,055,762
                         projects
 Research &       PCIW and             23,000                          50,500
 development /       Research
 capacity building      Institute
 Sustainable water    IRSA and WAPDA    33,416,443        421,959       76,210,312      1,309,490       1,439,433
 resource                for the purposes of
 management,        water
 monitoring & flood    management  and
  mitigation services   CEA/CFFC      for
                        coordination of
                         flood      irrigation
                        services
 Promotion of         Pakistan Council        780,412         904,198        960,000        108,460        119,306
 energy and            of Research in
 Water              Water
 Conservation        Resources
 and Water
 Quality
 (Research)
 Total                                   99,275,009      3,756,335     137,491,469     4,505,228      4,954,776

Page 227

   5. Key Performance Indicator/ Targets

                                        Target
              Key Performance               Planned Target         Mid-Term Target  Outputs                           Achieved
                      Indicators
                                      2023-24      2024-25      2025-26    2026-27    2027-28
Climate resilient Number of Small Dams to be                -
Water          completed
infrastructure    Number of Medium Dams to be     In Process
development     started
             Number of Large Dams to be        In Process
                  started
Sustainable      Total Water Storage Capacity               -
water resource
management,
monitoring &
flood mitigation
services
Promotion of    No. of R&D Projects                 14
energy and      Operation of Research Farms (7       7
Water           Nos.)
Conservation                  Training of Farmers/end             250
and Water                users/community (persons)
Quality                   Desertification Control and            70
(Research)                 rainwater harvesting activities
                  (Nos.)
                Capacity Building of staff of          400
               Water Supply Agencies and
                  professionals (Persons)
                  Monitoring of Bottled Water          4
                  throughout the country (no. of
                  Quarters per year)
                 Monitoring Water Quality Health        3
                   of Major Rivers (Nos.)
                 Annual Report, Newsletter,          35
                     Brief Handouts, Research
                  Reports, Paper and
                   Publications (No.)

              PNC-IHP meetings (Nos.).            1
                  Fabrication and distribution of        7000
                 technologies like microbiological
                   testing kits. etc. (Nos
               Groundwater Investigation            45
                 Services (Nos.).
                 National Water Quality             16000
                 Monitoring throughout field
                  laboratories (No. of Samples)
                Drinking/Waste Water Testing

Page 228

National Assembly:
PAO: Secretary

1.      Goal: Smooth functioning of legislation

2.      Policy:

3.     Outcomes:

4.     Budget by Outputs
                                                                                                In Rs. 000’
                                Actual                                        Budget           Medium Term Budget
     Output        Office    Expenditure
                              2023-24      2024-25     2025-26      2026-27       2027-28
  Overall             Main            4,522,515       5,135,079      8,328,550        8,367,739         8,367,739
  effectiveness of the   secretariat
  National Assembly

  Committee         Main            2,458,981       7,601,673      7,961,575        5,644,264         5,644,264
  effectiveness /        Secretariat
  Public Accounts
  Committees /
  Research etc.

  Total                              6,981,496      12,736,752    16,290,125      14,012,003       14,012,003

5. Planned and delivered Key performance targets

                                         Target      Planned
              Key Performance                              Medium Term Target  Outputs                           Achieved      Target                      Indicators
                                       2023-24      2024-25    2025-26   2026-27    2027-28
Overall            Meeting of National               50            130          130         130          130
effectiveness   of  Assembly (In days)
the      National   Facilitation to MNAs (No.of         300           310          310         310          310
Assembly        MNAs)
                                               71            90           95         100          100                         Bills passed (Numbers)
                                               13            35           40          45           45
                   Resolutions (Numbers)

                                               226           250          300         330          330                   Notices (Numbers)
                  Questions received in Sectt        2057          5500         6000        6500         6500
                 (Numbers)
                                               86            235          275         300          300
                  Motions (Numbers)

Committee        Meeting of Public Accounts         14            50           60          65           65
effectiveness      /  Committees (Numbers)
Public  Accounts   Monitoring and                    4             10           11          12           12
Committees        /   Implementation committee
Research etc.      (Numbers)

Page 229

                               13             9           10          11           11
Sub committees of PAC
(numbers)

Standing Committee / sub-          28            300          350         360          360
Committees meetings
(Numbers)

Research and information for       306           250          290         300          300
parliamentarians in Pakistan
Institute for Parliamentary
Services (PIPS) on different
issues (Numbers)
Research papers,                208           245          250         260          260
Digest/Books and research
studies conducted by
National Assembly
Secretariat (Numbers)

Page 230

The Senate:
PAO: Secretary

1. Goal: Effective promulgation of constitutional framework
2. Policy:
3. Outcome:
4. Budget by Output

                                                                                                                      In Rs. 000’
                                 Actual                                         Budget          Medium Term Budget
     Output         Office     Expenditure
                               2023-24      2024-25     2025-26     2026-27      2027-28
  Administrative       Senate            3,264,528        5,178,202      6,174,623      5,699,760       5,699,760
  services to            Secretariat
  legislation (Senate)

  Overall             Senate            1,723,796        2,063,964      2,880,057      2,268,753       2,268,753
  effectiveness of the   Secretariat
  Senate

  Total                               4,988,324       7,242,166      9,054,680     7,968,513      7,968,513

     5. Key performance Indicators/targets

                                          Target    Planned
                 Key Performance                          Medium Term Target     Outputs                          Achieved    Target                         Indicators
                                        2023-24    2024-25    2025-26   2026-27    2027-28
Overall effectiveness of  Number of days, the          112          110
the Senate             Senate shall meet during
                     a year

                    Number of Senator to be       100          100
                               facilitated
                    Number of Chairmen          40           40
                        Standing Committees to
                     be facilitated

Page 231

National Anti-Money Laundering and Counter
PAO: Chairman

1. Goal:        The National Anti-Money Laundering and Counter Financing of Terrorism Authority supervises, coordinates
and promotes policies to protect the financial system against Money Laundering, Terrorist Financing and implementation of
Targeted Financial Sanctions related to proliferation financing.
2. Policy:      To protect Pakistan from the threats posed by Money Laundering and Financing of Terrorism and Proliferation.
We hope to achieve this by implementing a robust and well-coordinated AML/CFT/CP regime; thereby, strengthening the financial
sector and economy, as well as ensuring safety and security in Pakistan and globally.
3. Outcome:    Pakistan's exit from FAT and compliance of FAT standards by synergizing national effort and providing
consistency and permanence in the field of Anti-Money Laundering, Terror Financing and predicate offences (Human and Drug
 trafficking, Hawala/Hundi and Tax Evasions).
4. Budget by Output

                                                                                                                      In Rs. 000’
                                 Actual
                                         Budget          Medium Term Budget
     Output         Office     Expenditure
                               2023-24      2024-25     2025-26     2026-27      2027-28
 NATIONAL ANTI-   NATIONAL                  -                        -           200,000
 MONEY            ANTI-
 LAUNDERING &   MONEY
 COUNTER        LAUNDERIN
  Financing of      G &
  terrorism authority   COUNTER

  Total                                                         200,000

     5. Key performance Indicators/targets

                                          Target    Planned
                 Key Performance                          Medium Term Target     Outputs                          Achieved    Target                         Indicators
                                        2023-24    2024-25    2025-26   2026-27    2027-28
NATIONAL      ANTI-   Continuity of efforts
MONEY LAUNDERING   against ML/TF
& COUNTER Financing   Compliance of FATF
of terrorism authority     Standards

                         Coordination among
                    LEAs & Relevant
                        agencies
                        Implementation of
                          National Action Plan
                         derived from National
                         Risk Assessment

Page 232

Special Investment Facilitation Council
PAO: Secretary

1. Goal:       To act as Single Window, for multi-domain cooperation in relevant field with GCC countries, in particular, and
other countries in general, for facilitation of investment and development of enabling policy environment.
2. Policy:          All economic and investment related policies
3. Outcome:   GDP growth, increase in exports and forex, speedy industrial development
4. Budget by Output

                                                                                                                      In Rs. 000’
                                 Actual                                         Budget          Medium Term Budget
     Output         Office     Expenditure
                               2023-24      2024-25     2025-26     2026-27      2027-28
  Special Investment   Special                       -                        -           843,382
  facilitation services   Investment
                             facilitation
                       Council

  Total                                                            843,382

     5. Key performance Indicators/targets

                                     Target    Planned
              Key Performance                           Medium Term Target   Outputs                       Achieved    Target
                     Indicators
                                    2023-24    2024-25     2025-26     2026-27     2027-28
Investment          Local                   Achieved     10            On-Going      On-Going      On-Going
Promotion     &   Seminars/Conference                  Conferences
Facilitation                                                          at Major cities

                    Foreign Seminars        Achieved     10           12           13           15
                                                        Conferences   Conferences   Conferences   Conferences
                                                      Abroad     in  Abroad     in  Abroad     in  Abroad     in
                                                                     Different         Different         Different         Different
                                                     Economic     Economic     Economic     Economic
                                                            Sectors        Sectors        Sectors        Sectors
                    Marketing       Material   Achieved     On-Going      On-Going      On-Going      On-Going
                      including  development
                       of       Documentary,
                    broachers,  flyers,  pitch
                  books etc.
Enhanced             Facilitation in 8 targeted   Nil             Establishing    Continuation    Continuation    Continuation
opportunities        sectors of economy                   6     country   of  remaining   of  remaining   of  remaining
domestic     and                                       desk              activities   of   activities   of    activities   of
foreign       direct                                                            the  previous   the  previous   the  previous
investment                                                                 year           year           year
Ease   of  Doing   Establishment    of   6   Nil               Facilitation in   Facilitation in   Facilitation in   Facilitation in
Business      by   country/regional desk                 8    targeted  8    targeted  8    targeted  8    targeted

Page 233

creating   country                                             sectors     of   sectors     of   sectors     of   sectors     of
desks                                             economy      economy      economy      economy
Showcasing     of  Two domestic and two   Nil            Recruitment    Investment     Investment     Investment
Investment           international events  for                    of 77 Project   Promotion      Promotion      Promotion
Opportunities        investment for promotion                    Staff           through    6   through    6   through    6
                                                                             country desk    country desk    country desk

Page 234

Cannabis Control Regulatory Authority
PAO: Secretary

1. Goal:
2. Policy:
3. Outcome:
4. Budget by Output

                                                                                                                      In Rs. 000’
                                 Actual                                         Budget          Medium Term Budget
     Output         Office     Expenditure
                               2023-24      2024-25     2025-26     2026-27      2027-28
 CANNABIS        CANNABIS                  -                        -           200,000
 CONTROL &      CONTROL &
 REGULATORY     REGULATO
  services         RY
                 AUTHORITY

  Total                                                            200,000

     5. Key performance Indicators/targets

                                          Target    Planned
                 Key Performance                          Medium Term Target     Outputs                          Achieved    Target
                         Indicators
                                        2023-24    2024-25    2025-26   2026-27    2027-28
CANNABIS CONTROL
&    REGULATORY
services