The text below was extracted automatically from the text layer of the official PDF. Line breaks and table layout may differ from the original, and where FBR scanned the paper and added a machine-read text layer, that layer can contain misread characters. Check the official PDF before relying on any wording or figure.
Page 1
GOVERNMENT OF PAKISTAN
MINISTRY OF FINANCE, ECONOMIC AFFAIRS, STATISTICS & REVENUE
(REVENUE DIVISION)
***
Islamabad, the 19th January, 2009.
NOTIFICATION
(CUSTOMS)
S.R.O. 41(I)/2009.- In exercise of the powers conferred by section 19 of the
Customs Act, 1969 (IV of 1969), and clause (a) of sub-section (2) of section 13 of the Sales
Tax Act, 1990, and in supersession of its Notification No. S.R.O. 316(I)/2007, dated the 12th
April, 2007, the Federal Government is pleased to direct that capital equipment (plant,
machinery, equipment and accessories), if not manufactured locally, shall be exempt from
the whole of customs-duty and sales tax if imported for the development of projects in the
Special Industrial and Economic Zones and for establishing projects in these Zones, subject
to the following conditions, namely:-
(i) locations and perimeters shall be notified by the Board of Investment
of Investment Division;
(ii) the benefit of this notification shall be admissible only for capital
equipment (plant, machinery, equipment and accessories), and not for
raw materials;
(iii) the goods imported under condition (ii) for the zones will not be
removed without the permission of the FBR within five years of their
importation;
(iv) in case of partial shipments of machinery and equipment for setting up
a plant, the importer shall, at the time of arrival of first partial
shipment, furnish complete details of the machinery, equipment and
components required for the complete plant, duly supported by the
contract, lay out plan and drawings; and
(v) Board of Investment (BOI) shall certify in the prescribed manner and
format as per Annex-A that the imported goods are bona fide project
requirement. In case the clearance of the imported goods is through
Pakistan Customs Computerized System (PaCCS), the authorized
officer of the BOI shall furnish all relevant information online to
PaCCS against a specific user ID and password obtained under section
155D of the Customs Act, 1969 (IV of 1969). In already computerized
Collectorates or Customs stations where the PaCCS is not operational,
Page 2
the Project Director or any other person authorized by the Collector in
this behalf shall enter the requisite information in the Customs
Computerized System on daily basis, whereas entry of the data
obtained from the customs stations which have not yet been
computerized shall be made on weekly basis.
Explanation.- In this notification,-
(a) the expression “machinery” means,-
(i) machinery and equipment operated by power of
any description, such as is used in industrial
process;
(ii) apparatus and appliances, including metering
and testing apparatus and appliances specifically
adopted for use in conjunction with machinery
and equipment specified in sub-clause (i);
(iii) mechanical and electrical controls and
transmission gear adapted for use of goods
specified in sub-clause (i); and
(iv) component parts of machinery and equipment,
as specified in sub-clauses (i), (ii) and (iii),
identifiable for use in or with machinery; and
(b) the expression “not manufactured locally” means the
goods which are not listed in the locally manufactured
list, notified through a Customs General Order issued
by the Federal Board of Revenue from time to time or,
as the case may be, certified as such by the Engineering
Development Board.
Annex-A
[See clause (v), First paragraph]
Header Information
NTN or FTN of Importer Approval No.
(1) (2)
Details of input goods (to be filled by the authorized officer of the Goods imported (Collectorate of import)
Regulatory Authority)
HS Description Customs- Sales Quantity Collect- CRN Date of
Code duty rate Tax rate imported Orate or CRN or
(appli- (applic- Mach Mach
cable) able) No. No.
Specifications WHT Quantity UOM
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
Page 3
Certificate.- Before certifying the above-authorized officer of the Regulatory
Authority shall ensure that the goods are genuine and bona fide requirement of the
project and that the same are not manufactured locally.
Signature: ________________________
Designation: ________________________
NOTE:- In case of clearance through Pakistan Customs Computerized System
(PaCCS), the information shall be furnished on line against a specific user I.D. and
password obtained under section 155D of the Customs Act, 1969.
[C.No. 1/9/Mach./92]
(MUHAMMMAD AFZAL BHATTI)
ADDITIONAL SECRETARY
Which later SROs refer to this one?
SROs whose FBR title names SRO 41(I)/2009, usually to amend or rescind it.
- SRO 934(I)/202430 June 2024Rescinding SRO,41(I)/2009 , dated 19.01.2009
Related Customs SROs on other
- SRO 404 (I)/200924 May 2009The Federal Government is pleased to extend, up to the 30th June, 2009 the period for which warehoused goods may remain in the warehouse
- SRO 271(I)/200928 March 2009The Federal Board of Revenue is pleased to approve the proper places in the customs Sheikh Zayed Airport, Rahim Yar Khan.
- SRO 269(I)/200928 March 2009The Federal Board of Revenue is pleased to approve the proper places in the customs airport (Dera Ghazi Khan Airport), Dera Ghazi Khan.
- SRO 42(I)/200919 January 2009Incentive Package for the development of Pak-China Investment Zones
- SRO 1250(I)/20086 December 2008the Federal Government is pleased to extend up to the 31st December, 2008, the period for which warehoused goods may remain in the warehouse;
- SRO 558(I)/200810 June 2008Release of past financial securities filed by WAPDA, KESC, Sui Northern / Southern Gas Company.